Education - School Building cost
School Building cost
S.N |
Description |
Quqntity |
Units |
Rates |
Amounts Rs |
01 |
Earthwork in Excavation |
10469.00 |
Cu.ft |
5.00 |
52345.00 |
02 |
Earth Back filling |
13259.00 |
Sq.ft |
3.00 |
39777.00 |
03 |
Flat brick soiling |
5046.00 |
Sq.ft |
25.00 |
126150.00 |
04 |
P.C.C |
1665.42 |
Cu.ft |
205.00 |
341411.10 |
05 |
R.C,C |
6185.98 |
Cu.ft |
225.00 |
1391845.50 |
06 |
Reinforcement |
21650.93 |
Kg |
100.00 |
2165095.00 |
07 |
Form work |
15351 |
Sq.ft |
30.00 |
460530.00 |
08 |
Brick Work |
9223.00 |
Cu.ft |
165.00 |
1521795.00 |
09 |
Telia tile flooring |
9791.10 |
Sq.ft |
65.00 |
636421.50 |
10 |
Cement Skirting |
1478.40 |
Sq.ft |
22.00 |
32524.80 |
11 |
Plastering on wall, Ceiling |
1478.40 |
Sq.ft |
30.00 |
547041.00 |
12 |
Liun Plaster |
7920.00 |
Sq.ft |
12.00 |
95040.00 |
13 |
Wall Paints |
18235.00 |
Sq.ft |
13.00 |
237055.00 |
14 |
Enamel Paint |
3489.00 |
Sq.ft |
11.00 |
38379.00 |
15 |
Wooden Railing |
175.00 |
Sq.ft |
450.00 |
78750.00 |
16 |
Wooden handrailing |
18.00 |
R.ft |
475.00 |
8550.00 |
17 |
Wood Work for Frame |
248.20 |
Cu.ft |
1600.00 |
397120.00 |
18 |
Wooden Roof with Thatch |
3686.00 |
Sq.ft |
400.00 |
486000.00 |
19 |
Glazing window |
1620.00 |
Sq.ft |
300.00 |
486000.00 |
20 |
Flush Door Shuttering |
672.00 |
Sq.ft |
500.00 |
336000.00 |
21 |
Ceramic tile |
850.00 |
Sq.ft |
85.00 |
72250.00 |
22 |
Tiolet 2 rooms for B and G |
2 Nos |
|
70.000.00 |
70.000.00 |
|
Total in Nepali Rupees |
|
|
10608477.90 |